Director general of open joint-stock company Sangtuda-1 HPS has appealed to the Tajik government, attracting its attention on critical situation on the site.
DUSHANBE
, September 14, Asia-Plus – A critical situation has formed on the site for construction of the Sangtuda-1 power plant as the
Dushanbe
cement plant has suspended cement supplies to the site, a letter by Rakhmetulla Alzhanov, director general of open joint-stock company Sangtuda-1 HPS, sent to Tajik Prime Minister Oqil Oqilov said.
“The cement plant today suspended supplies to the site and if urgent measures are not taken the construction work will be suspended,” the letter said, noting that as of September 14, reserves of cement on the site have amounted to only 2,058 tons.
In his letter, the director general also noted that the
Dushanbe
cement plant now owes more than $6 million to the company.
Alzhanov solicited Tajik PM to hold an urgent meeting on this subject today.
GBAO and Khatlon province complete spring draft target early
Chronicle of the month: March, 2026
Donald Trump states US ready to end war with Iran without a Deal
Kyrgyzstan launches domestic production of national currency
Windy April: weather forecast for Tajikistan
Tajikistan faces continued religious freedom challenges
The Judo Grand Slam in Dushanbe: what to expect
New developments in Isfara: schools, power substation, and coal mine opened
Iran claims drone factory in Tajikistan, but no evidence surfaces
Nuclear raid or breaking the blockade: why Trump wants thousands of Marines and paratroopers off the shores of Iran
All news
Авторизуйтесь, пожалуйста