DUSHANBE, November 24, 2008, Asia-Plus -- Work on concreting arch of the Anzob Tunnel, linking the northern Sughd province and the central part of the country, was completed at the end of last week, according to the Ministry of Transport and Communications (MoTC).
The source at a MoTC said that work on installation of lighting facilities was also nearing completion. According to him, this work is expected to be finished by the end of this week.
He further added that the tunnel had been opened for traffic. As it had been reported earlier, the Istiqlol Tunnel, better known as the Anzob Tunnel, had still been closed for traffic since September 12 because of repairing works.
“Finishing work in the ventilation tunnel is also nearing completion,” said “Builders are currently working in three shifts in the ventilation tunnel.”
The tunnel, 5.5 kilometers in length, has been built with assistance of Iranian specialists.
We will recall that Iran’s Saber International has constructed the Istiqlol Tunnel. The total project cost was estimated at 40 million US dollars, and Iran has provided US$5 million in a form of grant and extended a loan worth US$21 million to Tajikistan. The tunnel makes the highway from Dushanbe to Khujand open for traffic the whole year round and drops the transit time by four to five hours.




GBAO and Khatlon province complete spring draft target early
Chronicle of the month: March, 2026
Donald Trump states US ready to end war with Iran without a Deal
Kyrgyzstan launches domestic production of national currency
Windy April: weather forecast for Tajikistan
Tajikistan faces continued religious freedom challenges
The Judo Grand Slam in Dushanbe: what to expect
New developments in Isfara: schools, power substation, and coal mine opened
Iran claims drone factory in Tajikistan, but no evidence surfaces
Nuclear raid or breaking the blockade: why Trump wants thousands of Marines and paratroopers off the shores of Iran
All news
Авторизуйтесь, пожалуйста